Skyrise — Weekly Status
Period: Mon 15 Sep–Sun 21 Sep 2025
Progress Overview
- Structure: Primary frame ~90% complete; remaining steel at crown/mech levels—no NCRs this week; torque audits passed.
- Envelope: Curtainwall live on Elevations B/C (Lv 58–66); first-article mockup approved; +36 panels set; one half-day wind hold (non-critical) [➊ RFI – Facade Installation].
- Electrical (Lv 50–100): Rough-in complete; feeders to SB-3 energized; megger tests within spec; 3 coordination clashes resolved with updated rack elevations [➋ Weekly OAC].
- Lighting (Level 125 communal): Design approved; fixtures released; rough-in/support steel start next week [➌ Lighting Design Tech Review].
- Landscape: Plans finalized; logistics/laydown cleared; field crew mobilizes next week (subgrade → sleeves/conduit) [➍ Final Landscape Approval].
Schedule & Critical Path
Overall tracking on plan; float ~+2–3 days. Facade pace improves with second crew + resequencing; no critical-path hits identified.
Risks & Actions
Wind holds on facade lifts → Dual crews, flexible elevation sequencing, maintain 1-day buffer inventory.